Critical Grid Upgrade for Potchefstroom
The planned interruption has been initiated at the request of national power utility Eskom to finalize essential infrastructure repairs and reintegrate critical electrical equipment into the regional transmission network
Transformer Energisation and Capacity Restoration
According to the official communication released by the municipality's Corporate Services and Communication Unit, the facility has been running on a single 132/88/66 kV transformer after a secondary unit was temporarily decommissioned to undergo technical maintenance and repairs
The primary objective of the scheduled shutdown is to energise and commission the refurbished second transformer
Operational Details and Safety Directives
The scheduled power interruption is slated to run for an estimated duration of one hour and thirty minutes, scheduled between 14:00 and 15:30
Municipal engineering officials have issued standard safety protocols advising all consumers and property owners to treat every electrical connection, appliance, and installation as live throughout the maintenance window
Municipal authorities expressed regret for the disruption caused to daily activities, noting that while temporary outages disrupt commercial and domestic routines, the energisation of the second transformer represents a decisive step toward stabilizing the long-term electrical network